Steps to decorate the house
Renovating the house is a long-term and cumbersome thing, so we must be one step at a time when decorating, so that the house can be renovated to decorate the house. Xiaobian here introduces the steps to decorate the house. I hope that Everyone is doing something related.
First, the early design
One of the things we have to do in the early design is to make a detailed measurement of your room, which is more accurate than the purchase of building materials, and it is more immune to hacking at the time of settlement.
The main contents of the measurement include:
1. Identify the area involved in the renovation process. Especially the tile area, wall paint area, wallpaper area, floor area.
2. Identify the main wall dimensions. Especially in the future, it is necessary to design the wall size of the furniture.
Second, the main body of the change
Entering the construction stage, the main body demolition is the first project, including the demolition of the wall, the shovel wall, the disassembly of the heating, the replacement of the steel window and so on. To put it bluntly, it is to put the framework of the construction site first.
Third, hydropower transformation
Between the two aspects of hydropower transformation and main body demolition, some rookies may not know, and the first measurement of the cabinet should also be carried out. In fact, the so-called cabinet measurement did not have any actual content. Because the wall and the ground were not treated, the cabinet designer could not give the specific design size, but only the water outlet and the hood socket reserved by the developer. Location, make some relevant suggestions. mainly include:
1. Look at the location of the hood socket to affect the installation of the hood later.
2. Look at the location of the water meter.
3. Check if the position of the water outlet is convenient for installing the sink later.
For the first measurement of the cabinet, a slightly experienced rookie can do it himself. After the completion of the waterway renovation, it is best to do the waterproofing of the bathroom. The kitchen generally does not need to be waterproof.
Some rookies have always thought that some ingredients should be in advance before the renovation begins. What the master said is that unless it is the main material needed for the main body to be dismantled, the entry time of the main materials such as ceramic tiles and large core plates should be after the hydropower transformation. Because the circuit transformation involves the ground slotting, if the position of the tiles and the large core board are not properly placed, it is very troublesome for the workers to move in and out.
Fourth, woodworking
Woodworkers, masons, and painters are the "three brothers" in the construction process. The basic order of appearance is: woodwork, mason (waler), painter. The basic appearance principle is who is dirty and who is first
Five, tiling
If the workers are too busy, the foreman will usually let the "Mason" go to the bricks when the "woodworking boss" is not over yet. This is normal because there is no conflict between the two.
The process of “Mason BB†operation also involves the installation of the following three links:
1. Installation of door stone and marble window sill. The installation of the stone can be done with the paving slabs. After the paving slabs, the installation of the marble sills is usually done after the window sills are completed. The marble workers will prepare the glass glue and seal the marble and window coverings with glass glue. It is.
2. Installation of floor drains. The floor drain was the first to appear in the home improvement hardware because he had to work with the floor tiles. Therefore, when rookies start to visit the building materials market, they should buy floor drains early.
3. Installation of the hood. The range hood is the first to appear in the home appliance. After the kitchen wall and floor tiles are laid, you can consider installing the range hood.
"Mason second child" left the scene, this time can be measured about the second time of the cabinet. Accurately, after the kitchen wall tiles are installed and the hood is installed, the cabinet can be measured for the second time.
Six, brush wall paint
Oiler's third child came into the field, mainly finishing the wall surface treatment, brushing the topcoat, painting the furniture for the "carpentry boss", etc. The rookie who prepared to paste the wallpaper only needs to let the "oiler's third child" plan in the post. The wall of the wallpaper can be processed at the base level.
At this time, when the "Boss", "Lady" and "Lao" have left the scene one after another, many rookies will think that their decoration is over. In fact, one third of them are not enough according to the number of links. The reason why everyone feels this is because the decoration that people generally understand is only the “construction link†of the decoration. In fact, the “installation link†of the decoration is also the main focus of the decoration.
Seven, kitchen and bathroom ceiling
As the head of the installation process, the kitchen and bathroom ceiling is still continuing the "packaging" of the home. At the same time as the kitchen and bathroom ceiling, the cabinet's moisture-proof ceiling lamps and exhaust fans (Yuba) should have been bought. It is best for the rookie to install the ceiling fan and the exhaust fan (Yuba) at the same time, or leave the thread and opening.
Eight, cabinet installation
After the ceiling is over, you can install it on the door of the cabinet. If you are successful, you can finish the day. At the same time, there is also a sink (not including the upper and lower water parts) and the gas stove. Before installing the cabinet, it is best to coordinate the property to pass the gas, because the gas stove needs to be tested after it is installed.
Nine, wooden door installation
On the second day of the cabinet installation, the wooden door should have been measured more than a month ago and can now be installed. If it is smooth, it is also a day's time. The hinges, door locks, ground suctions and rookies that should be installed at the same time should be prepared in advance.
[Remarks] The production cycle of wooden doors is generally one month. Therefore, in order to make the construction period close, it is necessary to let the wooden door manufacturers come to the door to measure the size of the door as soon as possible after the main body is dismantled. Regarding the handling of the door opening, everyone needs to pay attention to it. If the height of the door opening in the house is inconsistent, it is necessary for the worker to handle the contour to look good.
Ten, floor installation
The floor can be installed on the second day of the installation of the wooden door. If it is smooth, it is also a day. Floor installation needs to pay attention to the following issues:
1. Before installing the floor, it is best to let the manufacturer come to the door to investigate whether the ground needs to be leveled or partially leveled.
2. Before the floor is installed, the floor of the pavement floor should be cleaned to ensure the dryness of the floor, so do not use water during the cleaning process.
Eleven, paving wallpaper
On the second day of the floor installation, the house was cleaned up and you could put it on the wallpaper. If it goes well, it will be the same day. If there are conditions, the floor should be protected on the day of wallpapering; it doesn't matter if there is no condition. It is no problem to hand over the wallpaper glue left on the floor to the pioneering cleaning. Before laying the wallpaper, try to do "do not have anything" on the wall.
Twelve, switch socket installation
The socket is connected to 3 lines, according to the left zero line right fire line, the ground line is inserted in the middle, the general socket has a representation, the fire line is L zero line is N, the ground line is a symbol. The switch is connected to the live wire at one end, and the other end is connected to the electrical or electric light, so that it can be
Thirteen, lamp installation
There is nothing to say about the lights. After the lamp is installed, the house will light up, saying goodbye to the glare of the 100-watt incandescent bulb during the renovation. It feels good.
Fourteen, hardware installation
The upper and lower water pipes, bathroom accessories, toilets, drying racks, etc., which were bought before, are all installed.
After the "big pieces" were installed, the home was still very "cool". After the lamps and hardware finals were installed, the family "lived" and really "lived". It is not an exaggeration to say that the first time you open the faucet and look at the flow of water and sputum, your heart will be beautiful; the first time you have a new toilet at home, you will feel a sense of accomplishment. By the way, you can give it a good name: "Virgo."
Fifteen, curtain rod installation
The installation of the curtain rod marks the basic end of the home improvement
Sixteen, pioneering cleaning
Do not install curtains before pioneering cleaning. When pioneering cleaning, do not have furniture and unnecessary household appliances at home, try to maintain more "flat", so that the pioneering cleaning can thoroughly sweep
Seventeen, furniture entering the market
The purchase time of furniture should be at the earliest after the completion of the hydropower transformation. In this way, we can choose the basic size range of furniture. Some rookies are already eager to order furniture before the renovation has begun, which is not necessary.
Eighteen, home appliances enter the market
At this time, the home appliance should enter the market, the installation of the installation, ready to stay
Nineteen, home softcover
Home accessories are the last step in the home improvement, and there have been renovations to the decoration, including the installation of curtains are part of the furniture accessories. As for buying curtains, it is best to order furniture to avoid style conflicts.
Furniture accessories also include consideration for buying some green plants, wall paintings, and crafts... In short, you can play freely after you stay. At this time, you have been promoted from a rookie to a master of decoration.
Name :marble Vinyl flooring (spc flooring,click spc flooring)
Board Thickness : 4.0mm
Wearing Layer Thickness :0.3mm,0.5mm as regular
Surface Texture :Deep Grain,Wood Grain,Marble Grain,Stone,Carpet
Finish :UV-Coating
Installation :Click system(Unilin,Valinge)
Delivery Time :15-25 days
Size:6''*48''(150mm*1220mm)
7''*48''(182mm*1220mm)
9''*48''(230mm*1220mm)
9''*60''(230mm*1525mm)
Backing Foam :IXPE(1.0mm,1.5mm,2.0mm) EVA(1.0mm,1.5mm)
Density :2.07kg/m3
Surface :Wood Embossed,Deep Wood Embossed,Handscraped,Eir.
Usage :Bedroom,Kitchen,Basements,Home,School,Hospital,Mall,Commercial to use.
Features :Waterproof,Wear resistant,Anti-slip,Moisture Proof,Fireproof,durable, anti-scratch, anti-bacterail.
Market :Export to American,Canadian,European Market,Part Asia,Africa Countries.Australia Market
Warranty :10 years for commercial and 25 years for residential
Stone Plastic Composite vinyl flooring is more and more popular new style eco-friendly vinyl flooring. SPC rigid flooring is set apart from other types of vinyl flooring by its uniquely resilient core layer. This core is made from a combination of natural limestone powder, polyvinyl chloride and some stabilizers.
SPC vinyl is a luxury vinyl flooring option with a structurally rigid, 100% waterproof core. SPC is also known as rigid core vinyl, and we use these terms interchangeably. Rigid core engineered vinyl flooring is designed to look like wood or stone, but requires less upkeep.
This flooring is durable, waterproof, and perfect for DIY installation. It`s ideal for both home and commercial areas.
Marble Grain Spc Flooring,Marble Grain Spc Floor,Marble Grain Spc Vinyl Plank,Marble Grain Spc Vinyl Plank Flooring
JIANGSU PERFECT NEW MATERIAL TECHNOLOGY CO., LTD. , https://www.bffloor.com